Digest>Sep/Oct 2013

Photo Caption:

Screw piles were used to correct the sinking foundation problem. These piles had to be drilled 77 feet into the ground before finding a composite soil foundation suitable to support the structure. They expected to find this soil foundation at 30 feet below the surface and the extra pile length, along with an additional 2-piles and labor, cost quite a bit more than expected.
Back to the edition of: Sep/Oct 2013

Story:

Restoration at Grosse Point
Back to the edition of: Sep/Oct 2013

All contents copyright © 1995-2025 by Lighthouse Digest®, Inc. No story, photograph, or any other item on this website may be reprinted or reproduced without the express permission of Lighthouse Digest. For contact information, click here.


USLHS Marker Fund


Lighthouse History
Research Institute


Shop Online












Contact Us   About Us   Copyright Foghorn Publishing, 1994- 2025   Lighthouse Facts     Lighthouse History